The climate changes
bring extreme weather conditions and unpredictable rains and floods to our
project sites. When heavy rain obstruct road work and earth slip occurs during
execution, the important question arises that which clauses of contract that has
to be invoked ?
Construction operations are often sensitive to
weather conditions such as temperature, humidity, wind, rainfall and snow. When
exceptional adverse weather causes construction delays and cost overruns,
contractors often submit claims, requesting extension to the project completion
time and compensation for extra cost, citing adverse weather as the basis for
their claims. many construction contracts include specific clauses that
regulate the basis and conditions for submitting weather-related claims. “If
adverse weather conditions are the basis for a claim for additional time, such
claim shall be documented by data substantiating that weather conditions
were abnormal for the period of time and could not have been reasonably anticipated,
and that weather conditions had an adverse effect on the scheduled
construction.” In other words, such clauses specifically stipulate that
weather-related claims should be supported by appropriate documentation,
substantiating that the weather conditions during construction were abnormal
and unexpected and that the encountered abnormal weather conditions had an
adverse effect on the construction schedule. The intensity of rainfall is
expressed by the total amount of rain accumulated during a given period of the
day. weather currently incorporates historical weather database for a period of
over certain period (30 years) obtained from historical weather data obtained
from the closest weather station to the site.
If the Contractor incurs cost or suffers a delay
as a result of unforeseeable physical conditions, he should firstly identify
the relevant Sub-Clause, which is Sub-Clause 4.12. Sub-Clause 4.12 is relevant
because it entitles the Contractor to extension of time and additional costs.
The test is then,whether the Contractor encountered Unforeseeable physical
conditions. All elements of Sub-Clause 4.12 must be met, which are:
• Physical conditions (climatic
conditions are not covered)
• Relevant physical conditions must
have been Unforeseeable (Unforeseeable is a defined term)
• Previous notice is required, which
should have been given as soon as practicable
• Claim notice is required according
to Sub-Clause 20.1 and 1.3
Let us see what Sub Clause 4.12 -Unforeseeable
Physical Conditions stipulates?
“ In this Sub Clause, “physical conditions”
means natural physical conditions and man-made and other physical obstructions
and pollutants, which the Contractor encounters at the Site when executing the
Works, including sub-surface and hydrological conditions but excluding climatic
conditions…”
Climatic conditions are left outside of above
Sub Clause, and if we go further, according to Sub-Clause 4.10 the Contractor
is deemed to have inspected and examined the Site and the surroundings and he
is also deemed to have been satisfied before submitting the Tender as to all
relevant matters, including the form and the nature of the Site and the
hydrological conditions. Also he may only consider the conditions to have been
unforeseeable in line with Sub-Clause 1.1.6.8, according to which Unforeseeable
means not reasonably foreseeable by an experienced contractor by the date for
submission of the Tender. (We can accept the Contractor as an experienced
contractor which he passes from the test of experience during pre-qualification
stage).
However two types of adverse physical conditions
must be distinguished. The Contractor may encounter conditions at the Site
which are (1) subsurface or otherwise concealed physical conditions which
differ from those indicated in the contract documents or (2) unknown physical
conditions of an unusual nature, which differ from those ordinarily found to
exist and generally recognized as inherent in construction activities of the
character provided for in the contract documents. Sub-Clauses 4.12 does not
define the term “adverse”. Thus it may be debated whether the Contractor can
rely on Sub-Clause 4.12 to shift the risk to the Employer where an
unforeseeable site condition is encountered, which is not an adverse physical
condition.
Obviously some of the risk which is inherent to
a construction contract does not depend on chance. It is then not insurable.
Thus differing ground conditions (see Sub-Clause 4.12) and unusual climatic
conditions (see Sub-Clause 8.4) which may have a critical impact on the
successful completion of the works are dealt with separately in FIDIC
contracts. This type of risk is also referred to as speculative risk. In
principle speculative risks are not unforeseeable. An experienced Contractor
should be able to foresee most of the current risks. The question is whether he
should also make allowance for the event that the risk occurs. Unforeseeability
is dealt with in Sub-Clause 1.1.6.8. According to Sub-Clause 1.1.6.8
unforeseeable means not reasonably foreseeable by an experienced contractor by
the date for submission of the Tender. The General Conditions refer to the term
unforeseeable as defined in Sub-Clause 1.1.6.8 in several Sub-Clauses, such as:
• Sub-Clause 4.6: Unforeseeable cost
• Sub-Clause 4.12: Unforeseeable
physical conditions
• Sub-Clause 8.4: Unforeseeable
shortages in the availability of personnel or goods
• Sub-Clause 8.5: Unforeseeable
delay or disruption
• Sub-Clause 17.3: Unforeseeable
operation of forces of nature
FIDIC strongly recommends consulting an
insurance expert prior to the conclusion of the contract. It is worth noting
that the decennial liability insurance must be obtained before the Commencement
Date. It is sometimes very difficult to obtain such insurance cover. Late efforts
to obtain such an insurance policy may delay the commencement of the works at
the risk of the Contractor.
As a rule the insured items (Works including
material to be used in performing the contract, construction plant and
equipment) are covered against any unforeseen and sudden physical loss or
damage from any cause not excluded.
A typical Contractors All Risk (CAR) claim will
be composed by three damage headings:
(1) direct loss(the costs to repair);
(2) prolongation costs to
the employer; and
(3) the prolongation or extended general conditions costs to the
contractor and subcontractors which may include loss of profits and expenses
caused indirectly by the event.
According to Sub-Clause 18.2(a) unless otherwise
stated in the Particular Conditions, the insurance for the Works shall be
effected and maintained by the Contractor as the insuring party and shall cover
all loss and damage from any cause not listed in sub-clause 17.3. The last part
gives a tool to the Contractor to claim his losses from the Employer for
unforeseeable operation of forces of nature. Sub Clause -17.3 Employer’s Risks
stipulates that ; “…. h) any operation of the forces of nature which is
Unforeseeable or against which an experienced contractor could not reasonably
have been expected to have taken adequate preventive precautions…”
Sub Clause 17.2 Contractor’s Care of the Works
gives exception in parallel to above as stipulates that; ”….If any loss or
damage happens to the Works, Goods or Contractor’s Documents during the period
when the Contractor is responsible for their care, from any cause not listed in
Sub-Clause 17.3 [Employer’s Risks ], the Contractor shall rectify the loss or
damage at the Contractor’s risk and cost, so that the Works, Goods and
Contractor’s Documents conform with the Contract….”
Sub Clause 17.4 Consequences of Employer’s Risks
stipulates that, “If and to the extent that any of the risks listed in
Sub-Clause 17.3 above results in loss or damage to the Works, Goods or
Contractor’s Documents, the Contractor shall promptly give notice to the
Engineer and shall rectify this loss or damage to the extent required by the
Engineer. If the Contractor suffers delay and/or incurs Cost from rectifying
this loss or damage, the Contractor shall give a further notice to the Engineer
and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to:
(a) an extension of time for any such delay, if
completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for
Completion], and
(b) payment of any such Cost, which shall be
included in the Contract Price. In the case of sub-paragraphs (f) and (g) of
Sub-Clause 17.3 [Employer’s Risks ], Cost plus profit shall be payable.
After receiving this further notice, the
Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or
determine these matters.
As conclusion, when landslides occurred and Works
damaged due to heavy rains, the Employers always expect from the Contractor to
cover his losses and also losses to the Works from the CAR policies. However,
the policies may not cover the losses in all circumstances. Also, in most cases
EoT is required to cover time losses. Therefore, you have to give timely notices
to the Engineer and also particulars of the losses subsequently, therefore you
do not loose your contractual rights.